05 Dec MMRDA – ROOFTOP TENDER 2MW
The rooftop of Mumbai Monorail Stations & Sites to be solarized with the capacity of 2 MW. The tender has been issued by MMRDA for the development of rooftop solar PV project of 2MW with the submission deadline of 26th Dec 2018.
Tender Highlights:
• Deadline for bid-submission: 26th December 2018.
• Project Development: RESCO mode.
• The scope of work: design, engineering, manufacturing, supply, storage, civil work, installation, testing, and commissioning.
• 25 Years O&M will be included.
• Estimated project cost: ₹120 million.
• Project completion time-frame: 12 months (from the issuance of the letter of allotment.)
*MMRDA – Mumbai Metropolitan Region Development Authority
#MumbaiMonorail #Solar #Renewableenergy #tender #Rooftop #MMRDA #RESCO #Mumbai #technology #energy